MARCH 2014 - OUR JOURNEY BEGINS!!
03/02/2014 Just out Jeepin' - Decided to checkout a new subdivision($150K Max FIRM!!)
03/03/2014 After an intense debate over a vaulted ceiling vs. functunality and kitchens, we decided on the Venice!!
03/06/2014 Signed contract with Ryan Homes for the Venice(Way more than $150K!!)
03/10/2014 Meeting with NVR to begin loan application process(Long and aggravating application process I might add!)
03/11/2014 Experienced some immediate 'contract remorse'
03/14/2014 Met with Sales Area Manager(He was nice but typical salesman for sure!)
03/14/2014 Rug Rite - Flooring selections
03/18/2014 Experienced SEVERE 'contract remorse' and decided to CANCEL(Yes you read that correctly!)
03/22/2014 Maybe switch to Florence?
03/23/2014 Maybe switch to a new subdivision?(Maybe too many excuses, I know!)
03/28/2014 Cancellation Meeting(But thrown some curveballs that we just couldn't pass up!)
APRIL 2014
04/02/2014 Signed the change orders and decided to stay in Venice!
04/08/2014 Ernest money turned in
04/10/2014 Guardian - Discuss phone/cable and surround sound pre-wiring
04/21/2014 Pre-Construction Meeting - FINALLY!
04/23/2014 Approved by NVR Mortgage(Did I mention I will NEVER use them again!?!)
04/28/2014 Lot Cleared!(Remind me to clear past 20 foot in the back, my temporary view will be SC Pines!)
MAY 2014
05/01/2014 Footers poured
05/14/2014 First stage plumbing
05/16/2014 Wood arrives onsite
05/19/2014 First stage plumbing complete & dirt leveled to pour slab
05/22/2014 Final slab poured
05/24/2014 First level begin framing
05/27/2014 Second level begin framing
05/30/2014 Locked rate with NVR
JUNE 2014
06/02/2014 Second stage heated plumbing
06/03/2014 Windows and doors installed also Guardian pre-wiring meeting
06/05/2014 Shingles Installed
06/06/2014 Pre-Drywall Meeting - insulation install
06/07/2014 Tubs Installed in spare bath and master bath and insulation complete
06/16/2014 Drywall begins
06/17/2014 Drywall installed
06/20/2014 Drywall taped, mudded and sanding down
06/23/2014 Driveway poured
06/24/2014 Kitchen cabinets installed
06/25/2014 Master bath tile surround installed, baseboards, siding started
06/27/2014 Siding complete, shutter installed, first coat of paint
JULY 2014
07/01/2014 Countertops installed, lights, AC unit, vinyl flooring, outlets
07/02/2014 Hardwood foyer, bathroom vanities
07/03/2014 Carpet installed
07/08/2014 Faucets, toilets, pedestal sink, master bath glass shower, garage door, deck, landscaping(we have cute little bushes and a tree too! :) )
07/10/2014 Sent final proofs & documents to NVR to submit for FINAL approval(It's not over yet!)
07/11/2014 Shelves installed in closets and pantry
07/12/2014 Started drywall repair and preparation for settlement
07/14/2014 Appliances arrived
07/15/2014 Blinds and back screen door installed
07/16/2014 Final touchups
07/21/2014 Pre-settlement Meeting
07/22/2014 Installed cabinet hardware, repainted front door, finished flowerbed around fire hydrant
07/23/2014 Closing!!!!
No comments:
Post a Comment